Google halts Belgium AI data center construction amid permit dispute
Construction halted
Google has paused construction of an AI data center in Farciennes, Belgium. The company stopped work pending further instructions. Authorities consider the company's operation a serious violation of the law.
The pause comes as the company faces accusations of operating without proper permits. The project has been subject to legal disputes for several months. The dispute began after Google requested a change to its building permit conditions.
Permit dispute
The company sought to change the cooling system from air cooling to a method that would draw water from the nearby Sambre river. Local authorities rejected this request. The company continued construction despite the rejection.
Local residents and environmental groups expressed concern. Greenpeace stated that continuing construction without a permit disrespects the environment, residents, and the law. The company's construction is scheduled for a court hearing next year.
Company statements
Google stated that it has operated in Belgium for over 15 years. The company stated that it remains committed to local laws. The company said that it is cooperating with authorities.
Data Center Map tracks approximately 13,500 data centers globally. Of these, 54 are located in Belgium. The United States has more than 5,200 data centers.